Project Background
Severe transformer capacity bottleneck. Local DSO requires 12‑24‑month approval procedure for transformer upgrade with high capital investment. Direct activation of all fast chargers will trigger transformer overload and trip‑off, making the station commercially unavailable.
Large fluctuating charging load pushes up energy expenditure. EV arrival concentrates at noon and evening rush hours. Simultaneous high‑power charging creates sharp power spikes, frequently triggering heavy demand‑charge penalty fees. Grid electricity price stays high during daytime, bringing high operational cost if fully powered by utility grid.
Local PV generation cannot be fully utilized. Solar car‑port produces abundant green power in daytime. However, EV arrival is random. Excess solar energy is fed back to grid with very low feed‑in tariff. There is no automatic scheduling logic to make PV energy supply EV charging as first priority.

Key equipment includes:
One set of MECC 1‑2 MWh grade containerized energy‑storage system. Phase‑1 configuration delivers 250 kW /522 kWh for power and energy supplement. Pre‑reserved expansion interfaces support future upgrade up to full 2 MWh when EV traffic grows. Inside container are integrated power‑distribution unit, liquid‑cooled thermal control, fire‑protection system and complete earthing protection, adapted to wide outdoor temperature range in Europe.
One unit of MECC ACCU‑200 micro‑grid coordination controller, millisecond‑level real‑time control hardware. It monitors grid power limit, sends charge‑discharge commands to energy‑storage system, and delivers power‑adjustment instructions to chargers for sequential charging. It strictly limits maximum power drawn from grid below transformer safety threshold of 420 kW to avoid transformer overload.
Multiple sets of high‑precision sensing assemblies including CT current transformers and multi‑function smart meters. Installed at transformer main incoming point, PV PCC point, ESS AC combiner cabinet and charger power distribution cabinet. Millisecond‑level acquisition for grid power, real‑time PV generation, battery SOC and real‑time power consumption of each charger, providing raw measurement data for all control algorithms.
One set of PV AC combiner cabinet, receiving AC output from 650 kWp PV car‑port inverters, performing AC power collection, surge protection and over‑current protection before connecting to onsite 400 V busbar.
One set of PV‑ESS‑charging AC grid‑connection combiner cabinet, equipped with circuit‑breaker, secondary surge protection and hardware overload protection device. It realizes power combination for liquid‑cooled cabinets, container BESS, PV system, EV chargers and utility grid. Hardware overload relay provides fail‑safe backup against software failure, together with EPO emergency shutdown interface.
One set of communication assembly including industrial Ethernet switch, 4G‑wired dual‑link and super‑capacitor backup power source. It guarantees stable communication among EMS, coordination controller, PCS, BMS, PV inverters and smart EV chargers, preventing scheduling failure caused by network fluctuation.
Eight third‑party 180 kW intelligent DC fast chargers, supporting remote power adjustment and receiving power commands from EMS to cooperate with sequential charging logic.
Core Technical Principles
1. PV‑priority for EV charging
2. Energy‑storage peak shaving and valley filling
3. Sequential charging control to prevent transformer overload
Coordination controller continuously monitors real‑time power at transformer incoming point. Total power imported from grid is strictly capped under 420 kW.
Closed‑loop energy‑flow logic
Commissioning & Operational Results
1.Successful commercial launch without transformer upgrade. Maximum grid import is firmly limited under 420 kW. High‑power simultaneous EV charging is supported by battery discharge. Expensive transformer reconstruction and long approval waiting period are avoided.
2.Noticeable operational cost reduction. Combined benefit of off‑peak battery charging and PV self‑consumption reduces monthly grid power purchase volume by 33%. Demand‑charge penalty risk is fully eliminated, lowering per‑kWh charging cost.
3.Greatly improved renewable energy self‑consumption ratio. PV self‑consumption rate rises from original 47% up to 86%. Large share of solar energy directly powers EV charging and realizes low‑carbon operation for highway service area.
4.Stable sequential‑charging performance. During rush‑hour heavy EV arrival, system automatically redistributes power flexibly. Transformer overload never occurs, all connected vehicles keep charging without abrupt interruption and guarantee good end‑user experience.
Project Significance & Industry Demonstration Value
Related Products
Liquid Cooling 125KW 261kWh Lithium Battery Energy Storage Cabinet
The IP55 Protected All-in-One Solar Energy Storage Cabinet is a high-performance, integrated energy solution engineered for outdoor commercial, industrial, and utility-scale solar applications. It integrates a 125kW Power Conversion System (PCS), a 261kWh lithium iron phosphate (LiFePO4) battery bank, an advanced liquid cooling system, and a intelligent Battery Management System (BMS) into a single cabinet with IP55 weatherproof protection. Designed to withstand harsh outdoor environments while delivering efficient energy conversion and storage, it supports solar energy absorption, peak shaving, load shifting, grid auxiliary services, and emergency backup power. Ideal for utility-scale solar farms, industrial parks, large commercial complexes, and remote microgrids, it provides a reliable, space-saving, and low-maintenance solution for large-scale renewable energy integration.






