Optical‑Storage‑Charging Demonstration Project For A Research Institute Project Overview

Aug 13, 2026 Leave a message

This project is located at a micro‑grid research institute in China. The institute applies a flat‑rate electricity tariff. On‑site photovoltaic and wind power are connected to the utility grid at 0.4kV, supplying power to building loads and charging piles.
 
The installed PV capacity reaches 300 kW, connected to the 0.4 kV distribution system via three sets of 100 kW inverters, operating under "self‑consumption first, surplus feed‑in" mode. A 5 kW wind turbine is mounted on the dormitory building, linked to the 220 V power network through five control‑integration all‑in‑one units. One set of MECC 125 kW/261 kWh liquid‑cooled energy storage cabinet is deployed and connected to the local 0.4 kV distribution busbar.
 

Charging infrastructure includes six units of 7 kW AC charging piles and one 80 kW DC fast charger, with reserved capacity for another 100 kW charging equipment. Electrical loads cover Building A, B, C and D, with peak load hitting approximately 400 kW.

 

 

2026-08-13100447916

 

 

 

On‑site Implementation Challenges & Technical Solutions

 

 

This is a retrofitting project based on existing distribution facilities instead of a new‑build site. Two typical technical obstacles emerged during installation and commissioning.
 
 
Challenge 1: Harmonic disturbance caused by multiple distributed energy sources, risking unstable operation of ESS and chargers
 
Multiple power‑electronic devices including PV inverters, small wind converters and EV chargers share the same 0.4 kV low‑voltage busbar. Frequent start‑stop of DC chargers amplifies harmonic distortion. Excessive harmonics may trigger unexpected protection trips of the energy storage PCS, resulting in intermittent charge‑discharge cycles and abnormal wind‑turbine inverter performance. Under such conditions, surplus PV power cannot be reliably stored.
 
Solution: The MECC 125 kW/261 kWh liquid‑cooled cabinet is embedded with active harmonic mitigation functions. Its PCS conducts high‑frequency real‑time sampling of bus voltage and current to dynamically compensate grid harmonics. From the system layout perspective, the energy storage cabinet is connected to the main 0.4 kV busbar rather than the branch circuit of charging piles, avoiding harmonic interference from EV charging equipment. The energy management system continuously monitors power‑quality indicators. Once harmonic values approach warning thresholds, it automatically adjusts ESS charge‑discharge power to suppress disturbances, enabling long‑term parallel stable operation of PV, wind turbine, energy storage and chargers without unplanned shutdowns.
 
 
Challenge 2: Heterogeneous devices with inconsistent communication protocols block coordinated dispatch
 
Existing PV inverters, wind turbine controllers and EV chargers are sourced from different manufacturers with mismatched communication protocols. Without a unified scheduling brain, surplus PV generation cannot be accurately identified. Energy storage cannot start charging immediately upon PV power surplus, leading to wasted renewable energy fed to grid, and delayed ESS discharging during peak consumption periods. Expected self‑consumption targets are hard to achieve.
 
Solution: The MECC energy management platform is equipped with multi‑protocol adaptive gateways, which are compatible with mainstream communication protocols of on‑site third‑party PV inverters, wind controllers and charging piles. Full‑link data communication is established among all hardware units. The platform collects real‑time data including PV output, wind generation, building load, charger power and ESS SOC. Global coordinated dispatch is realized instead of isolated device operation. The system detects PV power surplus at millisecond level and sends instant charge/discharge commands to energy storage cabinets, removing barriers for coordinated control among heterogeneous distributed energy assets.
 
 
 
Project Operation Strategy
 
 
Renewable energy consumption is set as top priority. During PV peak generation, when solar output exceeds total on‑site load demand, surplus photovoltaic power is stored in the MECC 125 kW/261 kWh liquid‑cooled cabinet to maximize PV self‑consumption rate. When PV output drops or night‑time peak load occurs, stored green electricity is discharged to supply building loads and EV chargers, reducing utility grid power purchase. Wind power surplus is also integrated into ESS scheduling logic.
 
 
 
Project Value & Impact
 
 

1.Boost renewable self‑consumption and cut electricity expenditure

 

The project addresses low PV on‑site consumption pain points and improves overall renewable energy utilization. Higher self‑consumption ratio reduces grid electricity purchase and brings tangible cost savings. The energy storage system retains expansion potential for future grid demand‑response and power‑trading revenue streams.
 
 

2.Support low‑carbon development and policy compliance

 

The solution aligns with national carbon‑peaking and carbon‑neutrality strategies and relevant green‑energy policies, creating eligibility for corresponding policy incentives.
 
 

3.Build replicable micro‑grid demonstration reference

 

As a physical testbed for the micro‑grid research institute, the project supports field tests covering ESS charge‑discharge strategy iteration, PV consumption optimization and multi‑source micro‑grid coordinated control. Real‑world operational data is accumulated to form standardized, replicable optical‑storage‑charging micro‑grid construction experience. It delivers practical references for similar projects among research institutes, industrial parks and science bases.
 
 
 

 

Related Products

 

Liquid Cooling 125KW 261kWh Lithium Battery Energy Storage Cabinet

 

The IP55 Protected All-in-One Solar Energy Storage Cabinet is a high-performance, integrated energy solution engineered for outdoor commercial, industrial, and utility-scale solar applications. It integrates a 125kW Power Conversion System (PCS), a 261kWh lithium iron phosphate (LiFePO4) battery bank, an advanced liquid cooling system, and a intelligent Battery Management System (BMS) into a single cabinet with IP55 weatherproof protection. Designed to withstand harsh outdoor environments while delivering efficient energy conversion and storage, it supports solar energy absorption, peak shaving, load shifting, grid auxiliary services, and emergency backup power. Ideal for utility-scale solar farms, industrial parks, large commercial complexes, and remote microgrids, it provides a reliable, space-saving, and low-maintenance solution for large-scale renewable energy integration.

page-1000-1000

Send Inquiry

whatsapp

Phone

E-mail

Inquiry